High-Performance Computing Center Stuttgart

Terra-Neo: Towards Earth Mantle Convection Simulation with Hierarchical Hybrid Multigrid Solvers

Visualization of velocity flowlines under the Himalaya mountain range; snapshot from a global convection model simulated with HHG.
Image: Terra-Neo Consortium

Convection in the Earth’s mantle is the driving force behind large scale geologic activity such as plate tectonics and continental drift. As such it is related to phenomena like e.g. earthquakes, mountain building, and hot-spot volcanism. Laboratory experiments naturally fail to reproduce the pressures and temperatures in the mantle, thus simulation is a key ingredient in the research of mantle convection. However, since simulating convection in the Earth’s mantle is a very resource consuming HPC application as it requires extremely large grids and many time steps in order to allow models with realistic geological parameters, researchers turn towards GCS supercomputers to tackle this challenge.

Read the complete user report at the Gauss Centre for Supercomputing.

Principal Investigator

Ulrich Rüde

Lehrstuhl für Informatik 10 (Systemsimulation), Friedrich-Alexander-Universität Erlangen-Nürnberg